Statewise Summary of Projects ( as on 30.04.2026 )


( All Amount in ₹ Crore )
S.No. State All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 ASSAM 119 2106.39 1461.28 1124.71 79 935.19 912.55 899.50 40 1171.20 548.73 225.21
Total : 119 2106.39 1461.28 1124.71 79 935.19 912.55 899.50 40 1171.20 548.73 225.21