Projects Dashboard

Overall Summary of DoNER Schemes

All Amount in ₹ Crore

As on 30.09.2026
All States
S.No. Scheme All Projects Completed Projects Ongoing Projects Financial Expenditure on Ongoing Projects till 30.09.2026 Financial Expenditure yet to be made in Ongoing Projects as on 30.09.2026
No. Approved Cost No. Approved Cost No. Approved Cost
A B C D E F G H I = G - H
1 PM-DevINE 53 6503.14 5 615.46 48 5887.68 2344.36 3543.32
2 NESIDS-OTRI 1613 21336.28 1259 14089.43 354 7246.85 4273.75 2973.11
3 Special Packages 123 2189.93 79 935.19 44 1254.74 641.45 613.29
4 NESIDS-ROADS 130 6087.53 78 3333.40 52 2754.13 1195.89 1558.24
5 Schemes of NEC 1855 15075.08 1438 10953.77 417 4121.32 3226.51 894.81
Total : 3774 51191.96 2859 29927.25 915 21264.71 11681.95 9582.76