Projects Dashboard

Statewise Summary of Projects

All Amount in ₹ Crore

As on 30.09.2026
S.No. State All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 ARUNACHAL PRADESH 479 6545.82 4705.83 3953.37 355 3432.24 3005.10 2864.90 100 2691.74 1396.71 787.55
2 ASSAM 838 12272.36 8942.13 6681.37 572 6118.17 5597.86 5349.82 246 5943.55 3262.28 1258.30
3 DELHI 4 21.41 16.61 0.00 4 21.41 16.61 0.00 0 0.00 0.00 0.00
4 MANIPUR 462 5177.66 3887.60 3195.92 344 3153.16 2794.47 2736.41 109 1829.62 1018.81 422.92
5 MEGHALAYA 321 4924.01 3355.11 2736.68 238 2640.48 2373.36 2223.98 72 2218.21 950.33 484.86
6 MIZORAM 375 4617.86 3219.50 2793.86 297 2700.25 2358.63 2289.65 72 1822.21 792.35 438.96
7 MULTI STATE 9 645.39 430.57 275.63 4 268.87 267.81 250.39 5 376.52 162.76 25.24
8 NAGALAND 436 5346.03 4195.17 3428.32 346 3381.77 3043.26 2866.65 76 1822.99 1058.47 466.54
9 OTHER AGENCY 335 3636.33 3238.53 2799.65 179 1537.99 1339.14 1306.22 130 2052.94 1878.25 1475.64
10 SIKKIM 259 3376.63 2813.15 2283.53 226 2615.90 2400.34 1976.32 31 735.24 404.49 303.51
11 TRIPURA 256 4628.45 3149.76 2525.41 177 2723.55 2345.50 2137.97 74 1771.67 757.49 384.07
Total : 3774 51191.96 37953.96 30673.72 2742 28593.79 25542.07 24002.31 915 21264.71 11681.95 6047.61