Statewise Summary of Projects ( as on 30.04.2026 )


( All Amount in ₹ Crore )
S.No. State All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 ARUNACHAL PRADESH 232 1768.16 1476.11 1341.29 173 1131.26 961.83 935.09 46 383.22 314.62 206.54
2 ASSAM 236 1869.81 1550.86 1404.32 179 1503.43 1261.27 1254.46 53 352.66 284.93 146.10
3 MANIPUR 202 1558.07 1287.95 1220.78 146 1250.12 1077.84 1066.97 50 258.94 182.22 125.93
4 MEGHALAYA 179 1218.44 1021.97 928.71 136 933.64 834.84 816.66 41 274.53 178.78 103.70
5 MIZORAM 171 1446.82 1251.72 1177.94 131 1239.26 1095.25 1085.72 39 206.99 155.91 91.65
6 NAGALAND 254 1621.85 1362.15 1253.39 197 1331.44 1177.00 1149.45 49 267.33 175.35 94.13
7 OTHER AGENCY 328 3371.45 2935.65 2558.92 153 1303.32 1104.47 1071.98 151 2023.98 1810.41 1469.54
8 SIKKIM 122 685.10 597.86 542.81 101 555.40 505.95 492.88 20 124.71 89.91 49.93
9 TRIPURA 115 997.16 815.26 752.84 65 766.04 665.16 660.91 46 218.76 146.63 88.67
Total : 1839 14536.86 12299.53 11181.00 1281 10013.90 8683.60 8534.10 495 4111.13 3338.78 2376.19