Statewise Summary of Projects ( as on 31.03.2026 )


( All Amount in ₹ Crore )
S.No. State All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 ARUNACHAL PRADESH 24 760.94 542.57 240.77 15 357.64 350.90 230.25 9 403.30 191.67 10.52
2 ASSAM 22 1465.85 1136.33 696.37 14 830.75 823.90 665.50 8 635.10 312.43 30.87
3 MANIPUR 11 462.52 272.30 162.53 2 132.94 131.52 123.72 9 329.58 140.78 38.81
4 MEGHALAYA 10 679.33 411.78 255.54 6 417.69 373.79 246.80 4 261.64 37.98 8.74
5 MIZORAM 12 453.15 196.71 88.48 7 192.40 170.33 88.48 5 260.75 26.38 0.00
6 MULTI STATE 3 213.97 213.97 209.26 3 213.97 213.97 209.26 0 0.00 0.00 0.00
7 NAGALAND 22 1078.51 777.83 517.42 12 443.75 439.81 335.89 10 634.76 338.02 181.53
8 SIKKIM 12 398.59 315.66 195.96 6 168.36 168.06 130.79 6 230.23 147.60 65.17
9 TRIPURA 11 486.11 320.89 97.38 6 263.01 237.31 77.18 5 223.10 83.58 20.20
Total : 127 5998.98 4188.04 2463.71 71 3020.52 2909.58 2107.87 56 2978.46 1278.46 355.84