Statewise Summary of Projects, as on 31.05.2025
All Amount in ₹ Crore
S.No. | State | All Projects | Completed Projects | Ongoing Projects | |||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
No. | Approved Cost | Financial Expenditure | Amount Utilised | No. | Approved Cost | Financial Expenditure | Amount Utilised | No. | Approved Cost | Financial Expenditure | Amount Utilised | ||
1 | ARUNACHAL PRADESH | 24 | 763.16 | 442.23 | 240.77 | 13 | 318.14 | 311.74 | 214.96 | 11 | 445.02 | 130.49 | 25.81 |
2 | ASSAM | 19 | 1379.36 | 1001.80 | 696.37 | 12 | 758.96 | 738.94 | 628.30 | 7 | 620.40 | 262.86 | 68.07 |
3 | MANIPUR | 10 | 444.32 | 203.92 | 162.53 | 1 | 118.20 | 116.78 | 116.78 | 9 | 326.12 | 87.14 | 45.75 |
4 | MEGHALAYA | 8 | 481.18 | 363.41 | 255.54 | 5 | 282.09 | 263.80 | 218.00 | 3 | 199.09 | 99.61 | 37.54 |
5 | MIZORAM | 9 | 287.49 | 158.22 | 88.48 | 3 | 62.28 | 53.91 | 45.44 | 6 | 225.21 | 104.30 | 43.04 |
6 | MULTI STATE | 3 | 213.97 | 213.97 | 209.26 | 3 | 213.97 | 213.97 | 209.26 | 0 | 0.00 | 0.00 | 0.00 |
7 | NAGALAND | 21 | 1059.50 | 677.29 | 517.42 | 9 | 322.56 | 310.69 | 271.66 | 12 | 736.94 | 366.60 | 245.76 |
8 | SIKKIM | 8 | 329.44 | 255.07 | 195.21 | 5 | 148.54 | 149.15 | 123.29 | 3 | 180.90 | 105.93 | 71.92 |
9 | TRIPURA | 7 | 347.80 | 299.85 | 96.99 | 2 | 43.94 | 43.94 | 43.55 | 5 | 303.86 | 255.91 | 53.43 |
Total : | 109 | 5306.23 | 3615.76 | 2462.56 | 53 | 2268.69 | 2202.92 | 1871.24 | 56 | 3037.54 | 1412.84 | 591.32 |