Statewise Summary of Projects, as on 31.05.2025


All Amount in ₹ Crore
S.No. State All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 ARUNACHAL PRADESH 24 763.16 442.23 240.77 13 318.14 311.74 214.96 11 445.02 130.49 25.81
2 ASSAM 19 1379.36 1001.80 696.37 12 758.96 738.94 628.30 7 620.40 262.86 68.07
3 MANIPUR 10 444.32 203.92 162.53 1 118.20 116.78 116.78 9 326.12 87.14 45.75
4 MEGHALAYA 8 481.18 363.41 255.54 5 282.09 263.80 218.00 3 199.09 99.61 37.54
5 MIZORAM 9 287.49 158.22 88.48 3 62.28 53.91 45.44 6 225.21 104.30 43.04
6 MULTI STATE 3 213.97 213.97 209.26 3 213.97 213.97 209.26 0 0.00 0.00 0.00
7 NAGALAND 21 1059.50 677.29 517.42 9 322.56 310.69 271.66 12 736.94 366.60 245.76
8 SIKKIM 8 329.44 255.07 195.21 5 148.54 149.15 123.29 3 180.90 105.93 71.92
9 TRIPURA 7 347.80 299.85 96.99 2 43.94 43.94 43.55 5 303.86 255.91 53.43
Total : 109 5306.23 3615.76 2462.56 53 2268.69 2202.92 1871.24 56 3037.54 1412.84 591.32